COSASE Probes Delays On NSSF’s Temangalo Land Project:Legislators Question NSSF Over Delayed Pension Towers Completion.COSASE Orders Further Inquiry Into NSSF’s Temangalo Land Usage.
Officials from the National Social Security Fund appeared before Parliament’s COSASE committee to address growing concerns over stalled development projects. Lawmakers raised sharp criticism regarding ongoing administrative and land-use hurdles surrounding the Temangalo affordable housing initiative, as well as prolonged completion delays on the Pension Towers project, renewing broader questions about the fund's investment strategy and management capabilities.
Following an audit report that highlighted persistent execution setbacks, officials from the Fund appeared before Parliament’s Committee on Commissions, Statutory Authorities, and State Enterprises (COSASE) today. Lawmakers grilled NSSF executives over the progress of the mixed-use development, raising serious questions regarding the fund's investment decisions, audit compliance, and overall project management.
Appearing before Parliament’s Committee on Commissions, Statutory Authorities, and State Enterprises (COSASE), NSSF officials were pressed to explain ongoing setbacks regarding the 463.87-acre Temangalo estate. Purchased in 2008 from businessman Amos Nzeyi, the property remains embroiled in boundary and occupation disagreements between the vendor and the Fund, leaving parts of the site inaccessible for construction.
Legislators also raised concerns about the investment in the land, its allocation, and the fact that it is currently in use, questioning whether the Security Fund is aware of this. In response, the security officer confirmed that they were aware; however, the committee chair directed that a further investigation be conducted into the matter.
Delayed project timelines have repeatedly raised questions, including concerns about the Pension Towers, which members say has taken an unusually long time to reach completion. With the building still unfinished, legislators continue to question the reasons behind the prolonged delay. However, it was confirmed that the project would be complete in the following year.
Comment / Reply From
You May Also Like
Popular Posts
-
Gospel Vibz
- Post By FamilyTv
- March 12, 2026
-
Sunday Services
- Post By FamilyTv
- March 23, 2026
WHO WE ARE
C.O.U. Family TV is a Church of Uganda-founded Television station, fully registered and licensed for operation under the law of Uganda. Currently showing on DSTV (Channel 375) and StarTimes (Channel 282) reaching millions of Ugandans across over 805,000 households in 39 dioceses of the Church of Uganda countrywide. WHY US? Brand TRUST at the Family Level (the backbone of every society). Family LOYALTY Our viewership is anchored on loyalty that comes with a strong feeling of support or allegiance. Partnering with us offers unrivalled EMOTIONAL brand equity benefits, which distinguishes COU Family TV from other brands. COU Family TV has a significant positive impact on its viewers' PERCEPTION and ATTENTION in over Anglicans in the 39 dioceses of the Church of Uganda across the country, which are two very important consumer decision-making.Newsletter
Subscribe to our mailing list to get the new updates!